The Nepal Electricity Authority (NEA) has finalized a Sigma Con as the contractor for the Balanch-Attariya Transmission Line Project, reports The Kathmandu Post.
The Details:
- Signa Con was selected through a global tender. The contractor is currently carrying a study to find out the quantity of equipment that will be needed to execute the upgradation.
- The study will take 2 months. After the study report is presented to NEA, NEA will approve the report and the equipment will be imported.
- The contractor plans to start the upgrade from May and complete it by February 2019.
- This project will upgrade the power line linking the country’s far western region to the national grid, from single circuit to double circuit. This will allow the transmission of six-phase electric power from the current power of three-phase.
- After its implementation, the power line will be able to evacuate around 180 MW of electricity in the region.
Backstory:
- The Balanch-Attariya Transmission Line was supposed to be completed in 2014 but different factors pushed back the deadline until it came into completed in November 2017.
- It is currently transmitting electricity generated by the 30 MW Chameliya Hydropower Project developed by the NEA, and the 8.5 MW Naugad Hydropower Project developed by Api Power.
The Latest
-
Honor X9c Launched In Nepal — And Durability Ain’t All It’s About! *Phew*HIGHLIGHTS The Honor X9c Smart price in Nepal is Rs. 38,999 (12/256GB). It has the…
-
ZTE Blade A75 Launched in Nepal: Large Storage on a BudgetHIGHLIGHTS The ZTE Blade A75 4G price in Nepal is Rs. 13,999 (4/256GB). The phone…
-
ZTE Blade A55 with 90Hz Refresh Rate Launched in NepalHIGHLIGHTS The ZTE Blade A55 price in Nepal is Rs. 11,999 (4/64GB) and Rs. 12,999…