The Nepal Electricity Authority (NEA) has finalized a Sigma Con as the contractor for the Balanch-Attariya Transmission Line Project, reports The Kathmandu Post.
The Details:
- Signa Con was selected through a global tender. The contractor is currently carrying a study to find out the quantity of equipment that will be needed to execute the upgradation.
- The study will take 2 months. After the study report is presented to NEA, NEA will approve the report and the equipment will be imported.
- The contractor plans to start the upgrade from May and complete it by February 2019.
- This project will upgrade the power line linking the country’s far western region to the national grid, from single circuit to double circuit. This will allow the transmission of six-phase electric power from the current power of three-phase.
- After its implementation, the power line will be able to evacuate around 180 MW of electricity in the region.
Backstory:
- The Balanch-Attariya Transmission Line was supposed to be completed in 2014 but different factors pushed back the deadline until it came into completed in November 2017.
- It is currently transmitting electricity generated by the 30 MW Chameliya Hydropower Project developed by the NEA, and the 8.5 MW Naugad Hydropower Project developed by Api Power.
The Latest
-
Yamaha Blue Fest Officially Begins from April 10 in NepalHIGHLIGHTS Yamaha Nepal kicked off the Yamaha Blue Fest with exciting offers on bikes and…
-
Redmi A5 Arriving Soon in Nepal: Lowest in Price, Highest in Refresh RateHIGHLIGHTS Redmi A5 4G price in Nepal could be Rs. 11,999 (3/64GB) and Rs. 13,999…
-
Crossfire RMZ 250 Now in Nepal: What’s New Compared to the Outgoing RM 250?HIGHLIGHTS Crossfire RMZ 250 price in Nepal is Rs. 8.59 Lakhs. RMZ 250 is the…